How do you change the cost of a drop shipped item AFTER it has been fulfilled.

Comments

5 comments

  • Avatar
    Quan Vu

    Hi Jason,

    You're still able to modify the unit cost on POs after they've turned to "Complete" status. You may also modify the unit cost for the external inventory in the PIM.

    Let me know if this will work for your reporting needs.

    0
    Comment actions Permalink
  • Avatar
    Jason

    Thanks for the comment Quan. We did a fair amount of testing on this, and I not believe changing the cost on a PO that has already been completed changes the COGS for that item that comes across in the reporting. It's like that cost is logged for the "external lot" as soon as the PO is completed, and changing that cost does not come across in the reporting module.

    I'm not 100% sure on this, as it has been a few months since I tested, but I'm high 90s. I can test this again if you guys need me to.

    0
    Comment actions Permalink
  • Avatar
    Quan Vu

    Hi Jason, sorry for the delay in getting back to you. I just did some testing using the PO Line Item data source and I can confirm the change in unit cost on Dropship POs will update in the Reporting tool as well. Which data source are you using?

    0
    Comment actions Permalink
  • Avatar
    Jason

    We're using the Item Fulfillment data source. Let me do some more testing on our end, I was pretty confident in what we found, but with the delay in reporting it can be a bit of a pain.

    0
    Comment actions Permalink
  • Avatar
    Quan Vu

    Hi Jason, I'm going to create a ticket for this and contact you via ticket.